County approves final change order and closeout for Torrey Preserve utilities extension; construction cost reduced
Summary
Hardee County approved final change order and final pay application for the Torrey Preserve Utilities Extension after a series of deductive adjustments that lowered construction costs by $25,597.20.
Get email alerts on the Utilities Infrastructure topic
No spam. Unsubscribe anytime.
Hardee County staff told the board Jan. 16 the Torrey Preserve Utilities Extension project — which added roughly 3,030 feet of sewer force main and about 2,030 feet of potable water main along Bostick Road — is ready for final closeout and payment.
Capital projects manager Bobby Keane said crews installed water and sewer infrastructure, added fire hydrants and new active service connections and completed restoration work along Bostick Road and associated intersections. Keane reported the final change order reduces construction costs by $25,597.20 because several anticipated restoration items were not required.
Why this matters: the extension provides water and sewer service and fire protection to a developing area along Bostick Road and helps connect future phases of utility service in the Huachula Hills/Torrey Preserve area.
Board action: the commission approved the final change order and authorized staff to process final pay application No. 4 and close out the project. The vote was unanimous.
Provenance: project closeout and change order were introduced at transcript segment 6317.475 and the vote recorded near transcript segment 6599.285.