Commission authorizes FAA grant application for Coffeyville runway mill-and-overlay design
Summary
The commission approved a resolution to submit an FAA grant application and proceed with design-only tasking for a mill-and-overlay of Runway 17/35 at Coffeyville Regional Airport; staff said the project is estimated at about $5 million with FAA covering 95% of eligible costs.
Get email alerts on the Aviation Infrastructure topic
No spam. Unsubscribe anytime.
The Coffeyville City Commission authorized staff to submit an FAA grant application and move forward on design for a mill-and-overlay of Runway 17/35 at Coffeyville Regional Airport.
Why it matters: Airport pavement preservation is critical to safe operations and attracting aeronautical activity. The grant, if awarded, would fund the design phase and eventually construction when FAA funds are available; staff called this a roughly $5 million project with a 95% FAA and 5% sponsor match.
Discussion: Jared Powers, director of parks (presenting on the airport item), said airport staff completed a geotechnical analysis and received FAA notice to proceed with the grant application. Commissioners asked about runway closure duration and schedule; staff said design authorization is the current action and that construction timing depends on pooled FAA discretionary funds, with a late-2026 to mid-2027 timeframe discussed as possible if funding aligns.
Commission action: The commission approved Resolution R-25-60 to submit the grant application and proceed with design; recorded votes were read and the motion carried.
Next steps: Staff to submit the FAA design/grant application and coordinate schedule and funding once FAA notifies of award.