Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Eastern New Mexico Water Utility Authority: major pipelines, treatment pilot and restoration efforts are on schedule for 2031

2108952 · January 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Administrator Orlando Ortega updated the committee on construction progress for Finished Water 1, Raw Water 3 and other segments of the regional system, described a new Authority‑led restoration approach, and said the project remains on schedule for a 2031 completion.

Orlando Ortega, administrator for the Eastern New Mexico Water Utility Authority (ENMWUA), told the Water Policy Advisory Committee that major pipeline and treatment components of the regional water project are active and on schedule, with an overall target completion date of 2031.

Ortega said Finished Water 1 is ‘‘15 and a half miles of 33 inch pipeline’’ from northwest of Cannon Air Force Base to the proposed water‑treatment site. He said crews recently laid the last stick of pipe on that segment and that vault construction and valve installation are underway. He described a change in the…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans