Sparks adopts updated impact fee schedule for Northern Sparks; fire fee rises after Fire 6 cost update
Summary
The Sparks City Council adopted Resolution 3475 updating land‑use assumptions, the capital improvement plan and impact fees for Impact Fee Service Area 1 (Northern Sparks). Fees for sanitary sewer, flood control, parks and recreation and fire stations were revised; the fire fee rose substantially after project cost revisions for Fire 6.
Get email alerts on the Land Use Impact Fees topic
No spam. Unsubscribe anytime.
The Sparks City Council on Aug. 25 adopted Resolution 3475 to revise land‑use assumptions, a capital improvements plan and impact fee schedules for Impact Fee Service Area 1 (IFSA 1), a roughly 9,186‑acre area in northern Sparks, effective Sept. 1, 2025.
Amber, a planning staff member presenting the update, summarized the purpose: the IFSA program requires periodic reviews under NRS chapter 278B to ensure new development pays a proportionate share of capital infrastructure costs. "This area is located in Northern Sparks. It comprises of approximately 9,186 acres, and this does conform to NRS chapter 278B," Amber said. The update incorporates development activity through Dec. 31, 2024.
Key changes: The program covers four fee categories — sanitary sewer, flood control, parks and recreation (regional trails) and fire stations.
- Sanitary sewer: With little undeveloped sewer facility need remaining, the single‑family residential fee would rise from $231 to $280, staff said, reflecting fewer remaining units over which to spread costs.
- Flood control: Staff proposed a reduction for single‑family residential from $510 to $287 for the updated project list, noting most flood projects are completed or nearing completion.
- Parks and recreation (regional trails): The residential fee was proposed to go from $1,067 to $1,167 as staff refined linear‑foot costs and connected segments.
- Fire stations: The single‑family fee rose sharply from $387 to $1,164. Amber said the change reflected a new, higher cost estimate for Fire 6; the prior estimate was about $66,250,000, while the purchased land and building costs produced a revised price tag of about $131,620,000, which drove the increase in the per‑unit fee.
Staff outreach and approval: Planning staff presented the draft to the Builders Association of Northern Nevada, the Associated General Contractors and the Sparks Capital Improvement Advisory Committee. That advisory committee voted unanimously to recommend approval on July 17. Amber said the city expects the revised fees to take effect Sept. 1, 2025.
Council action: Councilwoman Vanderwell moved to adopt Resolution 3475 and the motion carried unanimously with all members present.
Ending: Councilors said they appreciated the clear presentation and the outreach to builders and contractors. The adopted changes will be used at building permit issuance beginning Sept. 1, 2025.