Paulding County announces private developer will build 35–40 hangars at county airport
Summary
County officials and the airport director described a public–private land-lease deal with LH Construction Group to build 35–40 hangars at the Holiday Northwest Atlanta Airport, with no cost to the airport authority and revenue from lease payments and fuel sales projected for the county.
Get email alerts on the Airport Hangar Development topic
No spam. Unsubscribe anytime.
Post 2 Commissioner Sandy Caker and airport leadership announced a public–private partnership to add hangar capacity at the Holiday Northwest Atlanta Airport.
"We are very excited to announce a public private partnership out here at the airport," Nate Shatner, airport director for the Holiday Northwest Atlanta Airport, told the Board of Commissioners. He said LH Construction Group will enter a long-term land lease with the airport authority and construct roughly 35 to 40 hangars, including about 30 T-hangars and 5 to 10 box hangars.
Shatner provided a timeline and financing details: LH Construction Group has "put the deposit down on the steel package," the firm expects the steel to arrive in December, plans to start dirt work in November, and aims to have the hangars ready by summer or fall 2026 "provided the weather and all the other stars line up." He said there is no cost to the airport authority or to taxpayers because LH Construction Group is fronting construction costs.
Shatner outlined the expected benefits: a steady revenue stream to the airport from land-lease payments and fuel sales, and additional ad valorem tax revenue to the county from aircraft and the new buildings. He also described the local demand for hangars: "there's a huge hangar shortage in Georgia and across The United States," and said about 40 pilots have been on the airport waiting list.
Commissioner Caker introduced the announcement and provided contact information for those seeking more information about the project.
No formal board vote on the land-lease agreement or construction contract appears in the meeting transcript; airport staff framed the item as an update and developer announcement rather than an action item for immediate approval.