Summary

Clear Creek County commissioners approved a contract with Wold Architects & Engineers to perform a comprehensive jail needs assessment that will examine renovation costs, alternative confinement options and regional contracting. County staff said the study could be complete by spring and is intended to inform a fiscally sound long-term decision.

The Clear Creek County Board of County Commissioners approved an agreement with Wold Architects & Engineers to conduct a comprehensive jail needs assessment study.

Why it matters: county staff described the county jail as nearing the end of its useful life and said confinement operations are one of the largest general‑fund drivers. The study will examine capital renovation costs, the legal/operational implications of contracting confinement to another jurisdiction, and alternatives such as downsizing or other regionalization options.

What the board approved - The board approved a professional services agreement with Wold Architects & Engineers for a study capped at $119,000. County staff said the firm was selected through a competitive RFP process and offered a combination of Colorado experience and a thorough proposed scope.

Scope and timeline - The study will assess the cost of renovating the existing jail, the operational implications of contracting with neighboring counties (bed rates, transport, court logistics), and options to reduce the county’s general‑fund confinement liability. Staff told commissioners that, depending on third‑party schedules, the analysis should be complete in Q1 or early Q2 of 2026.

Vote and next steps - The board voted to approve the contract in an action session. No substantive policy decision (renovate vs. outsource) was made; the study is intended to produce the information commissioners will use to decide.

Ending note: County officials said they view the study as necessary to weigh options that could materially change the county’s long‑term operating and capital needs for confinement services.