MSD Southwest Allen County Schools reports Homestead High renovation nearing completion; board selects Hagerman Group for new CTE building

MSD Southwest Allen County Schools Board of Trustees · October 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board heard progress photos and satellite comparisons showing major changes at Homestead High School, was told final remodel areas should be complete just after Thanksgiving, and approved Hagerman Group as construction manager-as-constructor for the district—areer and technical education (CTE) building.

The MSD Southwest Allen County Schools board received a progress update on renovations at Homestead High School and approved the Hagerman Group to serve as construction manager as constructor (CMC) for the district—areer and technical education building.

The project update, presented during the board genda by Doctor Saint John and a project presenter identified in the record as Mr. Wilhelm, included a side-by-side comparison of Google Earth images showing the site before work began (March 2020) and a recent August 2025 image. Presenters pointed to new roofing, expanded parking lots, resurfaced and striped lots, topsoil and landscaping going in, and upgrades to the football field and the former Legacy gym.

—————Mr. Wilhelm said the last remodeled areas, including the old gym and locker rooms, are expected to be completed just after Thanksgiving. He described exterior concrete work and mechanical screen wall fencing that will receive architectural panels, installation of ACM panels on remaining façades, interior finishes in the mezzanine and corridors, and landscaping work now under way.

The board also acted on a separate agenda item to select a construction manager for a new CTE building. Doctor Saint John told the board a five-member selection committee (three administrators and two board members) issued a request for proposals on Sept. 4, received proposals by Sept. 25, shortlisted three firms on Sept. 30 and interviewed candidates Oct. 15. The committee recommended the Hagerman Group for its CMC and CTE experience and for a project team the committee judged to be strong and collaborative. The district plans to finalize an agreement using a standard AIA CMC contract in a subsequent meeting.

Board members moved and seconded the selection and approved the recommendation by voice/hand vote; no opposition was recorded in the transcript.

Why it matters: The CTE building and the Homestead renovation affect instructional spaces and extracurricular facilities used by students at Homestead High and, once built, will house career and technical programs the district is developing.

Details and next steps: The district said final contractual details with the Hagerman Group will be completed at a later board meeting using a standard AIA CMC contract. The renovation timeline given to the board calls for the last interior remodeling areas to be completed immediately after Thanksgiving; other exterior finishes and landscaping were described as in progress. The selection record notes the committee pproach and interview dates; the district will return to the board to finalize the CMC agreement.