Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Health Clinic topic
No spam. Unsubscribe anytime.
Ocean Shores health clinic fit-out nearing completion; flooring set for early November
Summary
City staff reported that interior work at the community health clinic is progressing, with ceiling grids and painting complete, casework on schedule and flooring installation planned for Nov. 3. Staff said budget for the fit-out is tracking as expected.
Get email alerts on the Health Clinic topic
No spam. Unsubscribe anytime.
Becky, a staff member, told the committee that work on the city health clinic is "really starting to come together." She said ceiling grids are installed, painting and door jambs are finished and casework is on schedule. Flooring installation is scheduled for Nov. 3, and staff expect to turn the space over to the clinic for furnishings toward the end of the year.
Becky said the project remains on budget. Committee members who visited the site commented that the progress was substantial since their last visit.
No formal action was taken; the report was informational.

