County seeks $156,080 change order to extend TUSA consulting on radio project; Motorola to provide credits

October 29, 2025 | Paulding County, Georgia


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

County seeks $156,080 change order to extend TUSA consulting on radio project; Motorola to provide credits
Paulding County staff told the Board of Commissioners on Oct. 28 that a change order is needed to extend TUSA Consulting services while the county finishes testing of its radio system. Bofford, a county staff member presenting the item, said project delays beyond the county’s control required additional consultant time and county staff participation in resumed testing.

Bofford said TUSA submitted a worst‑case estimate for a $156,080 change order to extend services through March 31, 2026. He added Motorola Solutions has agreed to reimburse the county in the form of credits totaling $167,000 that county staff expect will cover the change order. “We finished up the testing a lot sooner than we anticipated,” Bofford said.

Bofford said the county negotiated the reimbursement with Motorola and that he expects an update on system progress at the Nov. 11 meeting. The item was presented for board consideration; no final board action is recorded in the public portion of the transcript.

Don't Miss a Word: See the Full Meeting!

Go beyond summaries. Unlock every video, transcript, and key insight with a Founder Membership.

Get instant access to full meeting videos
Search and clip any phrase from complete transcripts
Receive AI-powered summaries & custom alerts
Enjoy lifetime, unrestricted access to government data
Access Full Meeting

30-day money-back guarantee

Sponsors

Proudly supported by sponsors who keep Georgia articles free in 2026

Scribe from Workplace AI
Scribe from Workplace AI