Twinsburg outlines timeline to seek WPCLF loan, open bids for wastewater upgrade
Summary
City staff told council the wastewater treatment project advanced through Ohio EPA review and that the city will submit a WPCLF construction-loan application in December, advertise bids in early November and expects Summit County to share roughly $1.7 million of project costs.
Twinsburg wastewater staff told council on Oct. 28 that the city has cleared a major technical step and is preparing to seek a state construction loan and open bids for a multi-year wastewater plant upgrade.
The wastewater representative said Ohio EPA toured the plant in July and the city received its PTI (plan, technical information) in record time, which staff and consultant BNN said reflected the thoroughness of design work so far. "This is a project that's going to far outlast…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat