Council reviews $5.1 million low bid and $612,450 design‑admin amendment for Rock Hill pump station

Concord City Council · October 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council was presented bids for a new Rock Hill Church site water pump station; Harper General Contractors submitted the low bid of $5,096,000 and staff proposed a $612,450 amendment for Hazen & Sawyer to provide construction administration.

Council reviewed construction and professional‑services contracts for a replacement water pump station at the Rock Hill Church tank site.

City staff recommended awarding the construction contract to Harper General Contractors, the low bidder at $5,096,000, and presented a budget amendment to fund the project. Staff said earlier design work had reached near‑complete plans before constructability problems halted the previous procurement; council members asked why the cost rose from an earlier estimate of roughly $3.5 million, and staff attributed the increase primarily to site work and building up the site because of steep grades.

Staff also asked the council to approve a contract amendment with Hazen & Sawyer, the design engineer, for construction administration services at a cost of $612,450. Council did not record a formal roll‑call vote on these items in the provided transcript excerpt.

Staff said Harper had performed well on prior Hillgrove work and is working with the city on related projects.