Engineer: Trousdale County water treatment plants back online; hydraulic model flags low-pressure pockets
Summary
Midten Engineering reported Oct. 28 that Water Treatment Plant 1 is back online and WTP 2 is complete. The contractor will return to finish pumps; booster station plans remain pending state approval. A hydraulic model identified several low-pressure or low-grade areas that will require field calibration and follow-up.
Evan White, an engineer with Midten Engineering, told the Trousdale County Utility Board on Oct. 28 that Water Treatment Plant No. 1 is back online and Water Treatment Plant No. 2 is complete.
White said the contractor asked to leave and return to finish work on the pump station at Browning Branch; the contractor expects to complete the remaining work by June next year. White said the firm will…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat