Main Street extension update: design adjustments, right-of-way needs and utility costs highlighted

Wildwood Economic Development Committee · October 21, 2025

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported on preliminary Main Street extension designs Oct. 20 and said the project requires additional right-of-way and easements; the 2026 CIP includes budget authority for right-of-way work.

City staff presented a progress report Oct. 20 on the Main Street extension project and the preliminary design changes intended to connect Main Street through the Town Center and provide access to a new all-inclusive playground.

Tom Lee said the plan has been adjusted to incorporate an ADA-accessible parking area and a redesigned pathway leading to an inclusive playground. To construct the full design as presented, staff said the city needs right-of-way from seven north-side property owners and additional easements on the south side. The project was placed in the city's capital improvement program, with $200,000 shown in 2025 for right-of-way work and multi-year construction funding included in 2026–2028 in the current CIP documents.

Lee also cited a preliminary engineering estimate to underground utility lines on the north side that exceeds $2 million; staff said those undergrounding costs are not included in the current base construction budget but will be part of future discussions. Committee members discussed timing, developer coordination (noting a nearby private development known as N 38/Latitude) and whether the city should proceed without waiting on developer-driven improvements.

Several committee members urged the city to move forward on the public improvement without indefinite delay. Staff said the design accommodates a median cut allowing a westbound U-turn for park parking and that the design will be refined to address driveway lengths and other right-of-way details. The committee endorsed moving the design forward and asked staff to continue outreach to affected property owners on easement negotiations.

Provenance: Design presentation and discussion begin at 00:46:27 (approx. 02:78:07 in the transcript) and continue through the item recorded at 01:00:00.