Mill Creek council approves $~84,000 contract amendment to finish 2024-25 pavement project

Mill Creek City Council · October 29, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council authorized the city manager to amend the JB Asphalt contract to cover pay‑estimate overruns tied to unforeseen field conditions and additional traffic control and crack sealing; council vote was 6‑0.

The Mill Creek City Council on Oct. 28 authorized the city manager, after city‑attorney review, to amend the JB Asphalt Inc. pavement contract to cover additional pay‑estimate costs tied to a 2024 pavement preservation project.

Public Works Director Mike Todd said the original contract amount awarded in July 2024 was approximately $1.755 million. Pay estimate number five and measured as‑built…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans