Carroll County approves funds for repairs to historic Woodlawn Agricultural School
Summary
After presentations on the building's history and community value, the Carroll County Board of Supervisors voted to appropriate county funds to begin repairs at the county-owned Woodlawn Agricultural School building.
Get email alerts on the Woodlawn Ag Building topic
No spam. Unsubscribe anytime.
The Carroll County Board of Supervisors voted to appropriate funds to support repairs and restoration work at the historic, county-owned Woodlawn Agricultural School building following a new-business presentation that stressed the site's historic significance and community value.
Presenters told the Board the Woodlawn Agricultural School is the first agricultural vocational building established under the Smith'Hughes Act (1917) and that the structure โ listed on the historic register โ still contains original interior features that supporters want preserved. John Carpenter, representing Carroll County Agriculture, introduced several FFA students who described recent contest wins and plans to attend national competitions.
The county packet included a funding request and cost estimates for immediate repairs to the roof and exterior paint; presenters noted that contractors have inspected the building and described the structure as "structurally sound" but in need of protective repairs to prevent further deterioration.
During discussion, the board and staff identified possible funding sources including a $20,000 contribution from the Economic Development Authority (EDA) and proceeds from a recent county land sale. County staff said EDA participation would be permissible but the final funding source could be adjusted, and the county administrator was authorized to manage the appropriation at his discretion.
A supervisor moved to appropriate the requested funds; the motion was seconded and passed by recorded roll-call vote.
What happened next: Staff will work with the applicants and contractors to begin priority repairs (roof and exterior preservation) and will coordinate any EDA reimbursement or transfer from land-sale proceeds, per the Board's direction.
Why it matters: The building supporters said the structure is locally significant for education and workforce history and that repairs are needed to preserve original materials and to maintain public access for programs tied to county agriculture and youth development.