Committee approves design contract for Shear Road reconstruction, forwards grant agreement to council
Summary
The Public Works Committee approved a design-services award to Lochmuller Group and recommended forwarding a Surface Transportation Block Grant funding agreement to full City Council. Staff described the project scope and competitive MARC process for the federal funds.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
The Lee's Summit Public Works Committee approved a motion Sept. 8 recommending the city hire Lochmuller Group Inc. for design services on the Shear Road Reconstruction project from Ward Road to M-291.
John Pershing, staff engineer, described the scope as a near-full replacement of the corridor including a probable three-lane cross-section, sidewalks and stormwater improvements to improve sight distance and safety. The committee moved and approved an ordinance to award the professional services contract to Lochmuller Group for $1,249,297 and authorized the city manager to execute an agreement.
Staff also presented a Surface Transportation Block Grant application award related to the same Shear Road project and explained how federal transportation funds are competed and allocated through the Mid-America Regional Council. Michael Parks said the grant covers the federal share while the city will provide the local match; staff discussed the typical allocation process and noted Mayor Pro Tem Lopez sits on the MARC board. Committee members asked about vertical curves and safety concerns on the corridor; staff confirmed the project is intended to address those issues.
The committee voted to forward the STBG funding agreement (TMP-3410) to full council with a recommendation of approval.