Engineering lays out 2026 CIP: Bridal Road realignment, roundabouts, paths and reconstruction timelines

Public Works Advisory Committee · October 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Paul Telamonchuk, project manager supervisor in Engineering, presented the 2026 CIP schedule and key project timelines.

Paul Telamonchuk, project manager supervisor in the Engineering Department, presented the 2026 capital improvement program and timelines for design, right-of-way acquisition and construction.

Design projects beginning in 2026 include Bridal Road (Bryan Road) pavement and path upgrades (replace a 6-foot asphalt path with a 10-foot shared-use concrete path from White Magnolia Drive to Norwood Hills Drive) and Mexico Road resurfacing with a 10-foot shared-use path from Barrington Drive to Bello Creek Road. Paul explained the city successfully pursued federal funding and county road-board funding where eligible; when both federal and county matches are available the city's local share can be a small portion of design costs.

Major construction and right-of-way planning items noted in the presentation:

- West Terra Lane/Bridal Road realignment (land acquisition beginning in 2026; construction planned for 2028'29). The project includes a roundabout with bypass lanes to accommodate industrial traffic and reduce backups near the I-70 interchange; staff said the full project cost is substantial and requires significant right-of-way acquisition and environmental clearances.

- Tom Ginevra/N. Cool Springs roundabout (construction programmed for 2026, with a likely late-summer start after major local events) designed to improve peak-hour backups, reduce stop-and-go emissions (CMAQ-funded application) and improve safety.

- Egering Drive reconstruction (full rebuild with storm-sewer work and sidewalks linking Westhoff Park and City Hall) scheduled for construction in 2026.

- Hough Road Phase 2 (bidding late 2026 and construction likely in 2027) and Deer Road and Steer Road reconstruction segments on the program in 2026'27.

- Darden Greenway connection from Sports Park to Bluebird Meadow Park and an underpass under Highway K to improve trail continuity.

Paul and committee members discussed roundabout geometry and truck bypass lanes for the West Terra/Bridal configuration, federal Congestion Mitigation and Air Quality (CMAQ) funding, anticipated right-of-way and relocation timelines, and why the Bridal/West Terra project appears later in the construction schedule (large cost and complex property acquisitions near I-70 require multi-year land acquisition and environmental clearances). Several committee members requested a deeper follow-up briefing on the Bridal/West Terra plan with more detailed exhibits and numbers.

Ending: Paul said design and preliminary environmental work are proceeding and staff will begin land acquisition for the West Terra realignment next year; committee members asked to schedule a fuller briefing on that project.