Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Developer outlines 200‑MW Stateline solar project and safety plans at Edgar County hearing; no decision
Summary
The developer of the Stateline Energy Center presented site plans, economic projections, noise and safety analyses at a public hearing in Edgar County. Board members adopted hearing rules and admitted the application into evidence but did not take a final vote; the hearing was recessed to Oct. 20, 2025.
Edgar County held a public hearing Oct. 13 on Stateline Energy Center LLC’s request for a special‑use permit to build a 200‑megawatt commercial solar facility with an on‑site battery energy storage system on about 1,934 acres roughly 2.5 miles east of Paris.
The developer, represented by attorney Seth Upoff and senior development manager Ian Evans, presented a comprehensive application and witness testimony on project design, safety, noise and public‑health topics. The county board adopted hearing rules at the outset, admitted the developer’s written application as Exhibit 1 and a developer PowerPoint as Exhibit 2, and reserved a final decision for a later session; the hearing was recessed to Oct. 20 at 5:00 p.m. in Courtroom 1 of the Edgar County Courthouse.
The project as presented combines ground‑mounted solar arrays and a collocated battery energy storage system (BESS). "It is a solar and battery energy storage hybrid system," Ian Evans said, and he told the board the project would include about 15 acres for battery storage within the larger site. Evans said the developer expects the project to represent "a $400,000,000 capital investment into Edgar County," to create roughly 200 temporary construction jobs and to increase the local property‑tax base. He also stated the developer’s estimate that total property taxes over a defined period would be about $23 million, with roughly $13.3 million directed to local schools; he said a tax‑impact expert would testify later to those numbers.
Evans described site selection and mitigation measures: proximity to a high‑voltage transmission point of interconnection, planned setbacks that meet or exceed the county ordinance (including a 150‑foot minimum to nonparticipating residences and 50 feet to road rights‑of‑way), vegetative screening, locked gated access…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat

