Commission approves four‑way stop at Oak and Harrison, funds to come from non‑general sources
Summary
The commission approved installing a four‑way stop at Oak and Harrison to address pedestrian and crash concerns. Commissioners requested funding come from the Downtown Improvement Board (DIB) or Community Redevelopment Agency (CRA) rather than the city general fund; the DIB had offered to contribute and the motion passed unanimously.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
The Panama City Commission on Oct. 14 approved adding a four‑way stop at the Oak and Harrison intersection after multiple residents and downtown businesses requested the change for pedestrian safety.
Commissioner Hughes said the intersection's geometry and vehicle speeds make it a near miss for pedestrians. Staff presented a construction estimate of roughly $12,000–$15,000 to install stop signs and the required stop bars and to modify paver ribbon curbing to meet the Manual on Uniform Traffic Control Devices (MUTCD) standards. Because the work requires altering the paver ribbon and adding the stop bar, staff estimated 3–5 days of road closure for concrete and paver work.
The downtown improvement board (DIB) offered to help pay for the installation; commissioners discussed splitting funding between the DIB and the CRA rather than using the general fund. Commissioner Hughes moved to approve the four‑way stop with funding sources other than the general fund; commissioners approved the motion 5‑0.
What's next: Staff will coordinate with the DIB and CRA on funding commitments, finalize a written quote and schedule the work to minimize disruption.
Quoted from the hearing: "It was probably 12 to 14,000. And one of the issues is because of the pavers, we have to come in and make modifications to what is called the ribbon curb," staff said.