Hot Springs staff seek board approval for $84,425 change order on new water treatment plant

Hot Springs Board of Directors · October 29, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineering staff presented Change Order No. 9 to the new water treatment plant contract, covering 12 items and totaling $84,425. The amount exceeds the city manager approval threshold; staff said Christian Engineers recommended the changes and funding will come from the 2023 board-approved water bond/fund.

Todd Piller, engineering project manager, presented Change Order No. 9 for the city’s new water treatment plant. Piller said the change order contains 12 distinct items that Christian Engineers recommended and that the change order total of $84,425 exceeds the city manager’s approval limit of $60,000, necessitating board approval.

Piller told directors all documentation supporting the change order — itemized descriptions, engineer recommendation letters and related contract paperwork — will be included in the board packet. He said the changes are necessary and will be funded from the 2023 board-approved water bond/fund.

Directors asked whether any single item was materially larger than the others; Piller replied the items were relatively small individual adjustments and that full documentation is in the packet. The resolution (R25-201) will be before the board for action on Nov. 4.