City staff say construction access for Courthouse Road will be ready by January; three‑phase power timing under review
Summary
Staff told the Finance Committee that construction access to the Courthouse Road site is being built and that DEP permits and a developer agreement set January as an initial deliverable. The city is negotiating whether three‑phase power must be completed by January or can be deferred, and noted limited competitive bids so far for oversight.
Get email alerts on the Infrastructure Construction topic
No spam. Unsubscribe anytime.
A city staff member (Jared) told the Finance Committee he will provide a Q3 financial update on the Courthouse Road project and described recent progress getting construction‑road access in place, work tied to DEP permits, and public‑works efforts to make the road passable for construction vehicles.
Staff said the developer agreement originally required construction access and three‑phase power by January to allow the judiciary’s planned work to begin. Because the developer has shifted its schedule, staff are seeking flexibility on the power timetable and considering whether permanent power should be installed later to reduce short‑term city costs.
Jared said the city has kept time‑and‑materials logs in public works but those are not routed daily to city hall; he will coordinate to include the data in quarterly accounting updates. Staff also reported the city received only one bid for a clerk‑of‑the‑works contract at about $300,000 and are exploring negotiated or modified scopes to lower up‑front costs.
An attendee asked whether the city is tracking daily costs; staff confirmed public works keeps daily logs and that Courthouse Road expenditures will appear in Q3 and Q4 accounting updates. Staff projected the courthouse construction itself could begin as late as January 2028, giving staff time to complete design, bidding and oversight preparations.
Committee members did not take formal action; staff said they will return with a Q3 report and any proposed modifications to the developer agreement.