Kokomo board approves $264,475 pay application and $15,989 change order for Fire Station No. 6
Get AI-powered insights, summaries, and transcripts
SubscribeSummary
The Board of Public Works and Safety approved Pay Application No. 3 for $264,475.25 and Change Order No. 2 for $15,989 on the Fire Station No. 6 reconstruction project. Acting city engineer Carrie Strainingen said the change order covers lighting modifications and extra storm sewer and steel work; $13,919.75 was set aside for retainage.
Carrie Strainingen, acting city engineer, presented pay application No. 3 and change order No. 2 for the Fire Station No. 6 reconstruction project.
"Work completed to date includes concrete footing, footers and pads, foundation walls and insulation, the storm sewer material delivery, submittals and erosion control," Strainingen said. She said Change Order No. 2 covers a lighting modification as well as scope changes and additional storm sewer and steel work. She recommended approval of pay application No. 3 in the amount of $264,475.25 and change order No. 2 in the amount of $15,989, and asked that $13,919.75 be placed in escrow as retainage.
A board member moved to approve pay application No. 3 and change order No. 2 for Fire Station No. 6; a second followed and the board approved the motion by voice vote. The transcript records the verbal "Aye" and the chair stated, "Motion carries."
