Summary

City staff and the fire department presented a revised design package and an itemized list of reductions for the proposed Lakeville fire station aimed at lowering cost while trying to preserve core functions.

City staff and the fire department presented a revised design package and an itemized list of possible reductions intended to lower the new fire station's cost while preserving core operations.

Chief Meyer said staff and the architectural/engineering team reviewed the schematic design and identified multiple opportunities to reduce area and cost, describing “roughly 3,200 square feet, roughly 1,200,000 in reductions” in early site and floor-plan modifications.

The proposed adjustments include a smaller public parking footprint on the north side; a reduced fitness area used primarily by firefighters; removal of a conference room and a wellness space in the residence wing (with some functions potentially relocated); elimination of operable partitions in a classroom; and a 4‑foot reduction in apparatus-bay length. Staff also identified small plan changes around the hose/training tower to achieve modest further reductions.

Consultants presented a numbered list of 15 deducts and alternates with line-item dollar amounts (snow-melt removal, fitness/locker reductions, conference-room deletion, rough‑in-only dorm plumbing, and switching some exterior walls from concrete block to metal stud). Staff reported that the combined deducts would reduce the project-cost estimate and provided a revised total estimate at the meeting.

Council members asked specifically about two tradeoffs: whether to include a snow‑melt system at apparatus aprons and whether to build dorm rooms now or rough‑in the plumbing and finish later. One councilor said plowing and manual snow clearing is intensive at apparatus doors, and another councilor favored building dorms now to avoid higher retrofit costs later; the mayor said he favored adding the dorms now if the budget allowed.

Staff said the consultant's current cost estimates include contingencies typical for early schematic documents and that contingencies will likely shrink as design advances into construction documents. The project team said sequencing could include alternates that the council could pick up if bids come in favorably.