Council approves $30,825 pump-control work to stop repeated bypass rentals

Helena City Council · October 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved a $30,825.27 estimate from Luckett Pump and Well Service to install a control panel intended to eliminate the need for two rented bypass pumps that have been repeatedly required at a water facility.

The Helena City Council approved an estimate of $30,825.27 from Luckett Pump and Well Service for work the water department said will remove the need for two rented bypass pumps at a critical pump station.

City staff said losing bypass pumps has forced repeated rental costs and occasional backups into a residential area. "This will get us off 2 bypass pumps," the presiding officer said during the water update; the proposal would install a panel to allow the city to stop renting temporary units.

Doctor Miller moved to accept the estimate for $30,825.27; the motion was seconded and approved on a roll-call vote. Staff said the city will formalize the expenditure with an ordinance as required by procurement procedures.

Council members emphasized that reducing recurring rental costs is a priority for the department and that the repair should prevent future backups and reduce operating expense.