Isanti County delays phase‑2 paving on County Road 5 roundabout project after utility/asbestos removal; board approves schedule revision
Summary
The board approved a schedule change that delays the phase‑2 pavement work on the County Road 5 roundabout project until next spring after crews found an abandoned asbestos‑coated gas line and experienced utility delays during construction.
County Highway Engineer Justin Bergerson updated the Isanti County Board on Oct. 21 about schedule changes to the County Road 5 (East Dual Boulevard) roundabout project (SAP 3605037) and other construction projects.
Bergerson said the project was initially value‑engineered and planned in two phases: finish the roundabout intersection first and complete pavement rehabilitation on adjacent segments in phase 2. During construction staff found an abandoned gas main with an asbestos coating that had to be removed inside the project limits, and the project experienced small utility…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat