Isanti County delays phase‑2 paving on County Road 5 roundabout project after utility/asbestos removal; board approves schedule revision

Isanti County Board of Commissioners · October 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a schedule change that delays the phase‑2 pavement work on the County Road 5 roundabout project until next spring after crews found an abandoned asbestos‑coated gas line and experienced utility delays during construction.

County Highway Engineer Justin Bergerson updated the Isanti County Board on Oct. 21 about schedule changes to the County Road 5 (East Dual Boulevard) roundabout project (SAP 3605037) and other construction projects.

Bergerson said the project was initially value‑engineered and planned in two phases: finish the roundabout intersection first and complete pavement rehabilitation on adjacent segments in phase 2. During construction staff found an abandoned gas main with an asbestos coating that had to be removed inside the project limits, and the project experienced small utility…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans