Committee reviews multiple street, stormwater and wastewater projects; approves several design and estimate requests
Summary
The operations committee received status reports on Osage/First, Union and Fourth street projects; Hawthorne Pond completion; Industrial/Midwest Drive stormwater needs; wastewater interceptor easement work; and directed staff to pursue grant applications and preliminary design/estimate work for several projects.
The City of Pacific operations committee on Oct. 30 reviewed progress on a suite of street, stormwater and wastewater projects and approved multiple staff follow-up actions, including a recommendation to reapply for a regional grant and requests for design-level and preliminary cost estimates.
Street projects: Staff reported the Osage and First intersection work is still expected to begin in early spring and Union Street design is complete and planned for bidding in December; Fourth Street was deferred to next year because of required easements. The committee voted to recommend applying for an East‑West Gateway grant for Highway N Phase 5 and approved a motion to forward that recommendation to the board for a formal application.
Preventative pavement maintenance: Committee members reviewed the Cochran PPMP multi‑year plan and noted that recent large grant-driven projects have consumed transportation funds, limiting…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat