CUSD 300 operations committee reviews Parkview asphalt, HVAC, elevator and IT contract recommendations; telecom switch projected to save roughly $326,000 over 3
Summary
CUSD 300 staff recommended multiple contract awards Oct. 14, including a $177,000 Parkview asphalt package, a $2.92 million rooftop unit replacement package, an elevator maintenance contract, and a three‑year Ivanti cloud migration priced at $308,746.64; staff also recommended a telecom provider switch projected to save roughly $326,000 over three years.
CUSD 300 staff presented multiple capital and service contract recommendations Oct. 14 at the Board Operations Committee meeting. Staff framed these items as part of routine capital maintenance and technology continuity work and asked the committee to forward recommendations to the full board for approval.
Facilities and construction
Staff reported that bid package 32A‑1 for Parkview asphalt work returned Schrader Asphalt Services as the lowest responsive, responsible bidder at $177,000; the project would be funded from Capital Fund 60. For rooftop and air‑handling unit replacements (three 90‑ton rooftop units at Jacobs High School and two aging units at Hampshire Middle School), staff reported nine bidders with a low bid from DeKalb…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat