PBBC approves $24,163 change order for Pollard library young adult project

Permanent Public Building Committee / School Building Committee (joint meeting) · November 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The PBBC approved a $24,163 change order from Tower Construction addressing additional demolition, shelving moves and storage for the Pollard library young adult project; committee approved the payment from the general contractor's budget by roll call.

The Permanent Public Building Committee on Nov. 3 approved a change order (Change Order #1) for the Pollard library young adult renovation project in the amount of $24,163 (rounded figure discussed in meeting). Committee staff said the work covered a set of small items including additional demolition of ceiling drywall to accommodate temporary walls, labor to relocate bookcases and shelving at the library’s request, and temporary storage of excess furniture during an online auction.

The chair moved that the committee approve the Tower Construction change order in the stated amount, noting nearly the entire value would come from the general contractor’s budget. The motion was seconded and passed by roll call. The committee recorded ayes from members present and will place the change order in the project file.

Nut graf: The change order consolidates several smaller scope adjustments necessary for contractor sequencing and library operations; the committee directed staff to continue oversight of submittals and schedule impacts.

Quote "We had to take down some extra demo work…move bookcases and shelving from the First Floor to the Lower Floor," a project presenter said when summarizing the items covered by the change order.

Ending The committee approved the change order and indicated the project is roughly one‑third complete and proceeding without major schedule concerns.

Provenance Change order discussion and motion: Nov. 3 PBBC meeting (presentation beginning at 00:12:00).