FPUA approves $250,000 contract for impact-rated windows at administration building

Fort Pierce Utilities Authority Board · November 4, 2025

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Fort Pierce Utilities Authority board unanimously approved a contract with Presco South Construction for up to $250,000 to replace windows at the authority's administration building, funded by a FDEM grant and scheduled for completion by June 30, 2026.

The Fort Pierce Utilities Authority on Nov. (date not specified in the transcript) authorized a contract with Presco South Construction for an amount not to exceed $250,000 to replace windows at the authority's administration building at 206 South Sixth Street.

"Staff recommendation for award of contract to Presco South Construction for, an amount not to exceed $250,000," said Mr. Rutherford, chief operating officer, as he presented the proposal and noted the new windows will be impact-rated for 170 miles per hour and be low-e, energy-efficient units. Rutherford said the project is fully funded by a FDEM grant and will begin immediately with completion no later than June 30, 2026.

Rutherford outlined the procurement history, saying the request for proposal was uploaded on 07/24/2025 and advertised on 07/28/2025 and 08/04/2025. He reported that vendors requested specifications and that a mandatory site visit was attended by several firms; the facilities manager recommended accepting the Presco South Construction proposal. Rutherford also stated that none of the respondents were local vendors.

A board member asked whether installation would require closing the downstairs office or otherwise impact the public. Rutherford said the work will be staged — "we'll likely have to do them one at a time" — and added, "we don't plan on closing anything." Following that exchange, a board member moved approval; the motion was seconded and approved on a roll call vote.

Votes at a glance - Motion to set the agenda: approved (roll call recorded affirmative votes). - Motion to approve minutes: approved (roll call recorded affirmative votes). - Motion to approve consent agenda: approved (roll call recorded affirmative votes). - Motion to award contract to Presco South Construction (not to exceed $250,000): approved (Mrs. Bennett — yes; Mrs. Davis — yes; Mrs. Gibbons — yes; Mr. Fee — yes; Chair — yes).

The director announced the next board meeting will be Nov. 18 at 4 p.m. in the chambers.