Intermediate school on schedule; board approves related change orders including $14,969 for rain‑garden remediation
Summary
District construction managers reported the intermediate school is on schedule across three construction phases. The board approved multiple construction change orders, including a $14,969 remediation for a stormwater BMP that intruded into new foundations and an ordered gate for the playground area.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
The South Fayette Township School District received an update on the intermediate school construction, with Draw Collective reporting the project is tracking to the contractor's baseline schedule and key work progressing across three project areas.
"As of today, we sit really on schedule where we thought we'd be," said Yosef of Draw Collective, summarizing progress in the three‑story addition (Area A), an enclosed wing (Area C) and foundations work in Area D. Area A has MEP rough‑in and drywall largely complete with finishing and painting planned; Area C's drywall is roughly 99 percent complete; Area D foundations and underground plumbing work are underway and steel erection is targeted for November.
The board reviewed two change‑order items tied to ongoing work. One is a level‑1 order to add a gate at the basketball courts to provide future access; the gate has been ordered but not yet installed. The second is a level‑2 change related to an unforeseen condition: an existing stormwater BMP/rain‑garden protruded into the planned foundation footprint and required excavation, removal of elements, capping of remaining components and reconnection of the system. The district recorded the cost for that remediation as $14,969.
Board members asked whether the rain‑garden location was reflected on as‑built drawings; Draw Collective said the installed BMP had expanded beyond the footprint shown on earlier documents and that the as‑builts did not reflect the condition. The presenter said he would follow up to identify the prior contractor and whether final as‑built drawings were submitted.
The board later approved five construction change orders on the consent agenda by voice vote. The meeting record identifies the change‑order approvals as passed but does not provide a roll‑call tally.
The presenter also noted minor photographic documentation is slightly dated and promised updated drone imagery at the next meeting. Work to complete finishes in Areas A and C is scheduled through December in order to turn those spaces over for use next semester.