City reports lower-than-expected Phase 2 GMP for Casper Business Center/police station after competitive bids
Summary
Staff reported a guaranteed maximum price for Phase 2 of the Casper Business Center/Police Station that is under prior estimates after competitive local bids and scope adjustments.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Chief Operating Officer Tom Brower reported that the guaranteed maximum price (GMP) for Phase 2 of the Casper Business Center / Police Station (core infrastructure: mechanical, electrical, plumbing, fire, etc.) came in below earlier, year-old cost estimates after competitive bidding and some scope changes.
Brower explained that parts of the earlier estimate were shifted to a later phase (Phase 3), which lowered the Phase 2 bid total, and that local contractors provided competitive pricing across many trades. He highlighted several items:
- Exterior windows and doors bids were significantly under the older estimate, producing savings. - Finishes and bathrooms scope were reduced to reflect the building's adaptation from an office design to a police facility (separate restroom needs and different finish requirements), reducing cost. - Certain costs (for example, a pump/pumping arrangement in the basement) were driven by site-specific conditions and were retained; other items such as a standby generator or rooftop assembly were shifted to Phase 3. - The plumbing/HVAC package had competitive bids and a contractor proposed an alternate vibration/"shaker" solution that could save several hundred thousand dollars; staff will evaluate that value engineering recommendation.
Brower said the city will carry a construction contingency (~8%) but expects to manage and return unused contingency if possible. Staff recommended executing the GMP and proceeding with material acquisition and subcontractor mobilization; awarding the contract was scheduled for a future regular meeting (Oct. 7) once final documents are ready.
Ending: Staff reported competitive local participation and recommended awarding the Phase 2 GMP to proceed toward construction, with additional updates and a subcontractor list to be provided after contract award.