Carefree UCFD approves $894,466 contract, 25% contingency for Silver Saddle pressure-zone pipeline

Town of Carefree Utilities Community Facilities District (Carefree UCFD) · November 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Town of Carefree Utilities Community Facilities District on an unanimous vote approved Resolution 2025-03 to award construction contract 2025-C01 to Judd Company LLC for the Silver Saddle Pressure Zone Pipeline Improvement Project, with a 25% contingency.

The Town of Carefree Utilities Community Facilities District on an unanimous vote approved Resolution 2025-03 to award construction contract 2025-C01 to Judd Company LLC for the Silver Saddle Pressure Zone Pipeline Improvement Project, with a 25% contingency.

C.J. Dimaggio, the town engineer, told the board the project will replace about 4,000 feet of aging 3-inch PVC mains with new 8-inch ductile iron pipe to create a pressure zone that will improve system flow and permit the installation of seven new fire hydrants in the Highlands.

"The Silver Saddle is where the tanks are," Dimaggio said. He described the work as creating "a zone of pressure in the water system rather than a pipeline itself," explaining that the larger…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans