The council approved a $69,138 contract with CSM Mechanical to refurbish grit-room force mains at the wastewater treatment plant and approved multiple DPS equipment purchases, including utility tractors and a multi-use utility vehicle, using budgeted CIP and replacement funds; staff said saving in-house labor and trade-ins reduced net costs.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Brighton — City council members approved several public-works contracts and equipment purchases on July 22, including a contract for wastewater pipe refurbishment and multiple replacement vehicles and implements for the Department of Public Services (DPS).
Deputy DPS Director Brooks presented a recommendation to award CSM Mechanical LLC the contract to refurbish grit-room sewer force mains, including sandblasting and new epoxy coating of selected pipes and valves. Brooks said the project originally drew a single over-budget bid in March, so staff reworked the scope and solicited new proposals; two bids in May produced a lower winning bid of $60,120 and staff requested a 15% contingency for a contract not to exceed $69,138. The council approved the contract.
Council also approved purchases from Hudson Incorporated under state contract pricing, including: a 2025 John Deere 1575 multi-use utility tractor (with attachments retained), a 2025 John Deere 5090E tractor with implements (trade-in applied), and a 2024 John Deere Gator utility vehicle (consent agenda amended to $22,909.68). Deputy Brooks and Superintendent Schroeder said retaining usable implements and using planned replacement schedules reduced long-term costs. Council approved the purchases by voice vote.
Council discussed trade-in values, the age and condition of existing machinery (one tractor dated to 1988/1987 at the wastewater plant), and the use of equipment for winter sidewalk clearing, sand-filter maintenance, and right-of-way work. Staff said some replacements were under budget after trade-ins and that retaining attachments would allow additional city crews to perform tasks currently contracted out.
Motions passed for each item; staff will move forward with procurement and schedule deliveries and trade-in dispositions according to the DPW replacement plan.