Brooklyn's Plaza: council approves playground and construction package after value-engineering cuts

Rochester Hills City Council · February 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a multi-vendor construction package for Brooklyn's Plaza that includes playground equipment, construction, construction engineering and design support after staff reduced costs through value engineering. Contracts total roughly $1.9 million with contingencies.

Rochester Hills City Council on Feb. 3 approved a series of contracts and a project budget for Brooklyn's Plaza that will add a fenced playground, improved splash-pad surfacing and site landscaping.

What was approved - Playground equipment and installation (Landscape Structures via Ventura, Brighton / contract for playground equipment): project budget $305,054.06 plus 5% contingency ($15,252.70) for a total not to exceed $320,306.76. - Construction contract (Lang Constructors, Flint): $1,319,648.09 plus 5% contingency ($65,982.40) for a total not to exceed $1,385,630.49. - Construction-phase design support (Niagara Murano, Rochester): $17,200. - Professional services and licensing fees (Gordian): $65,982.40. - Construction engineering (Spalding DeDecker): $175,856.

Staff said the package is a value-engineered version of earlier plans. "The original items that came in for this project ... were almost $400,000 more overall than what you see here," Parks staff said. The scope includes a fenced playground, shade area between playground and splash pad, surfacing improvements and a vegetative buffer along Auburn Road; staff emphasized the project will retain the plaza—s intended design while lowering cost.

Funding and timing The contracts were approved as individual procurement items with contingency amounts; staff said the project will start this spring pending typical scheduling and supply considerations and is expected to be completed this year.

Provenance: topicintro (02:06:17) "...Brooklyn's Plaza in the amount of $305,054.06..." topfinish (02:32:05) end of Brooklyn's Plaza items and votes.