CIP preview: Midtown Park phases, Old Hearn Road extension and South College reconstruction top proposed projects

Bryan City Council · July 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff reviewed the five-year capital improvement plan and a project database of more than 180 submissions. Major priorities included continued Midtown Park phases, the Midtown boardwalk and parking, Old Hearn Road extension, South College reconstruction, and various drainage and storm-sewer projects; funding sources include transportation/dr

City staff reviewed the capital improvement program (CIP) process and highlighted major projects being proposed for FY26–30. The CIP database contains over 180 project requests and staff said about $225 million of projects have funding or partial funding; the broader list totals near $955 million in requested projects.

Key projects and funding: staff called out Midtown Park Phase 3 (an $18.5 million allocation in the current plan for additional park components), the Midtown boardwalk and associated parking and amenities ($8 million boardwalk project plus other park funding), Old Hearn Road extension (construction contract and ongoing work to tie into new roadways), Commerce Street reconstruction and multiple road-widening and drainage projects. Staff noted funding sources vary and include certificates of obligation or bonds, transportation and drainage fees, general-fund transfers and utility fund contributions for water and sewer components.

District allocations and process: staff will provide one-page project summaries and a searchable project database to councilmembers; individual single-member district allocations were summarized in the presentation and staff offered to provide district-specific project lists for council review.

Next steps: staff said they will continue design work, finalize easements where required, and return with priorities for adoption alongside the FY26 budget; they also flagged that the city will re-evaluate CIP priorities in light of economic-development activity at the RELLIS campus.

Ending: staff asked council for feedback on priorities and said they will distribute project summaries and the database for council review.