Nixa council approves manhole lining, water‑tower solicitation and $450,000 micropaving contract
Summary
On July 8 the Nixa City Council approved three resolutions: a manhole lining contract not to exceed $160,500, solicitation of qualifications for water‑tower maintenance, and a micropaving contract not to exceed $450,000 to preserve roughly 3.5 miles of road. Council approved each by voice vote during the meeting.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
NIXA, Mo. — The Nixa City Council on July 8 approved three infrastructure measures as separate resolutions during the meeting.
Resolution 2025‑33 authorized the city administrator to execute a contract not to exceed $160,500 with Advanced Rehabilitation Technology LLC for manhole‑lining services. "We're gonna do about, 90 manholes this year to keep groundwater and stuff from polluting our sewer system," Water Superintendent Jason Stutzman said, describing the I&I (inflow and infiltration) reduction effort.
The council then approved Resolution 2025‑34, authorizing the city to solicit qualifications from engineering firms to perform required water‑tower inspections and maintenance under Department of Natural Resources rules; no contract dollar amount was included in the resolution. Stutzman said the city is required to inspect towers every five years and expects to select a certified engineering firm to perform cleaning, inspection and disinfection work.
Finally, Resolution 2025‑35 authorized a not‑to‑exceed contract of $450,000 with Donaldson Construction Company LLC for micropaving, a pavement‑preservation product. Street Superintendent Jeff Purcell said the work would cover approximately 3.5 miles and is intended to seal hairline cracks and add skid resistance without the higher cost of mill‑and‑overlay.
Votes and procedure: Each resolution was read, the council received brief presentations from department staff, and council members moved, seconded and approved each item by unanimous voice vote with all present saying "aye." The meeting record indicates the motions were made as follows: Resolution 2025‑33 (moved by Councilmember Aaron Peterson; second by Darlene Graham), Resolution 2025‑34 (moved by Kelly Morris; second by Zern West), and Resolution 2025‑35 (moved by Sean Lucas; second by Kelly Morris).
Financials and immediate effects: The manhole‑lining contract is not to exceed $160,500 and covers an estimated 90 manholes for I&I reduction. The micropaving contract is not to exceed $450,000 for about 3.5 miles of roadway preservation. The water‑tower item authorizes solicitation only; a future contract and cost will be brought back after qualifications are reviewed.
The record shows no public opposition to these items during the meeting and no recorded amendments. Work related to the three approvals will be managed by the public works and utility departments under standard procurement and contracting procedures.
The city clerk recorded the resolutions as passed by voice vote on July 8.