Construction underway for Athletics School; superintendent warns active electrical bid protest could delay March 2027 completion
Summary
Superintendent Raab reported construction activity at the Athletics School site and said a bid protest among electrical subcontractors is pending before the Attorney General's office, urging a fast decision to avoid schedule slippage toward the March 2027 substantial-completion target.
Get email alerts on the Construction Procurement topic
No spam. Unsubscribe anytime.
Superintendent Raab updated the committee on the Athletics School capital project, reporting that site work has begun (tree removal, fencing, on-site cranes) and that a formal groundbreaking is scheduled for Monday, Oct. 6. He said the district is already seeing on-site activity including generators and preparatory work.
Raab told members there is an active bid protest among three electrical subcontract bidders; the matter is scheduled for a hearing with the Massachusetts Attorney General's office the next day. He said the AG's review must be expedited so that subcontractor selection and downstream work are not delayed: "...we're really up against those deadlines to have the building completed." (Superintendent Raab). The project’s current substantial-completion milestone is March 2027, with limited wiggle room to April or May, he said.
The superintendent also described the immediate impacts on the site and the urgency of a timely AG decision: the district is operating with temporary generators now, and additional delays would force changes to the construction schedule and could push completion beyond the acceptable window.
The committee received the update; no vote was required. Administration said town counsel (Christopher Brown) will represent the town at the AG hearing and that the district will press for a prompt determination so contractors can proceed.
The committee requested continued updates as the AG process and subcontractor selection move forward.