Board approves interim housing contract as Serrano High modernization begins; timeline and costs discussed
Summary
Trustees approved a contract with Go Architects to design interim housing so Serrano High School can begin modernization. Staff outlined phasing, portable/modular plans, Measure J cash flow and possible use of a bond anticipation note if state funding timing changes.
The Snowline Joint Unified School District board voted to approve a contract with Go Architects to produce plans for interim housing at Serrano High School, a step district staff said is needed so modernization work can proceed while classes continue on campus.
Director of Facilities Bill Flynn said the interim housing plan calls for 14 leased portables (modular classrooms) to be sited where basketball and some tennis courts are now located so classrooms can be moved while the front office, parking and campus improvements are rebuilt. Flynn told trustees the interim housing contract will be submitted "over the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat