Council awards Williams Drive design contract amid questions about scoring and project funding
Summary
Council approved a professional services contract with Friese & Nichols for design of Williams Drive and large drainage works after members pushed staff to verify evaluation scores; the project is expected to focus on drainage improvements and will require separate construction funding decisions.
Get email alerts on the Transportation Drainage topic
No spam. Unsubscribe anytime.
Corpus Christi approved a contract with Friese & Nichols to design the Williams Drive extension and a major storm‑drain conveyance estimated in concept at roughly $48–50 million for construction, while the design contract was described as just under $2 million in the agenda memo. The design award followed questions from council about the firm’s “perfect” evaluation scores and whether the RFQ scoring had any clerical errors.
Lede: The professional services contract clears the way for design of a multi‑phase drainage and roadway project that city staff described as necessary to convey storm water off a large development tract and reduce erosion in the downstream ditch system.
Nut graf: Council members voiced concerns that the evaluation panel’s scoring produced unusually high rankings for Friese & Nichols; staff explained the scoring matrix (70% written submission, 30% interview) and said multiple city evaluators participated and that prior pre‑design work by Friese & Nichols made the firm familiar with site constraints. After staff confirmed the written tabulation, council voted to proceed.
Project scope and funding - Scope: Engineering services include conveyance design, culverts/box culverts, intersection and drainage improvements and phased construction. Staff said the work is primarily stormwater infrastructure rather than pure road widening. - Funding: The packet shows Type B sales tax funding for design (approximately $4.3M available), but no identified construction funds; staff noted the project could be a candidate for future bond programs or for the new one‑cent flood sales tax voters approved, and construction funding will be considered in future budget cycles.
Contested issue: procurement scoring - Council members asked for and received a staff explanation of scoring procedures. Staff and procurement said the tabulation reflected individual evaluator scores on the RFQ, converted pro rata to numeric totals; finance confirmed the tabulation was accurate and staff recommended against tabling the award. Council approved the contract after review.
Outcome: City approved authorization to negotiate and execute a design contract with Friese & Nichols and instructed staff to continue refining funding and phasing plans.
Sources: City engineering staff presentation, council discussion (Sept. 23, 2024).