Committee reviews contract change orders, solar design addition and highways work‑management system

Hawaii County Council Committee on Finance · November 4, 2025

Summary

Committee members questioned a 50% increase to an engineering contract to add photovoltaic design and reviewed two change‑order reports and an extension of a highways work‑management system (iWORKS). Members also received updates on Alpuni Center roof replacement and a multi‑change‑order swimming pool accessibility project.

The Finance Committee reviewed reports of authorized change orders and asked departments to clarify costs and project status. Finance transmitted change‑order reports (communication 24.21 and 24.22) that included: a requested 50% increase ($68,000) to an engineering contract to add photovoltaic (solar) design and to modify scope, fee and completion date following community feedback; multiple change orders on a swimming pool accessibility project; and a roof replacement at Alpuni Center where additional beams were found and replaced.

Charmaine Felipe, business manager for Parks and Recreation, confirmed the $68,000 increase was for the design portion to incorporate a photovoltaic system and community comments. "The purpose of the contract... amendment to modify scope of work, consultant's fee, method of payment, and project completion date following community feedback," Felipe said. She also noted that the pool accessibility project’s original contract was about $6.5 million with cumulative change orders totaling approximately $731,000, and that some change orders were tied to COVID‑19 supply issues.

Public Works business manager Kelsey Kalua Lewis described the iWORKS work‑management system used by the highways division, noting it tracks work orders, GIS data, inventory, and field photo capture using iPads and supports emergency response. When asked about a public‑facing component, Lewis said she would "have to go back and check with them." She also said highways uses a condition‑rating tool (Manley) to rate county roads and uses the iPads to capture before/after photos for emergency reporting.

Motions to close files on communications 24.21 and 24.22 were carried and forwarded later in the agenda. Committee members asked departments to provide more detailed documentation on the swimming pool project’s multiple change orders and to monitor contract increases closely.

Provenance: Topic introduced at 00:03:52 (communication 24.21) and last discussed at 00:12:00 (closing votes and follow‑up requests).

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source