City staff outlines construction timetable for Kidner Parkway, Crossley phases, Cheshire Road and utilities

Sunbury City Services Committee · November 6, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported multiple construction milestones: Phase 1 paving on Crossley expected in November 2025, Phase 2 in October 2026; emergency access for fire apparatus will be installed; a signal at the future Hitachi crossing is anticipated around 2027; pump station upgrades and sewer-lining work are scheduled to begin in January.

Philip provided a multi-item construction and development update, summarizing timelines and coordination needs for several projects in the southern part of Sunbury.

He said Crossley (the residential phase) is in active construction with Phase 1 paving expected to begin the week of the meeting (staff referenced a planned November 2025 paving start) and Phase 2 anticipated in October 2026. Staff will maintain an on-site construction…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans