Fulshear reports near-completion of Pecan Knoll water plant; staff explains 16-inch line outage
Summary
City staff said Water Plant No. 2 (Pecan Knoll) is nearly complete and partially operational pending power, and explained an afternoon outage caused when a contractor punched through a 16-inch city line while making a connection for an adjoining development.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
City staff told the Fulshear City Council on Sept. 16 that construction of Water Plant No. 2 (the Pecan Knoll facility) is nearing completion and that parts of the plant are already in temporary operation.
Staff reported the construction project was about 96% complete by days and about 89% complete by dollars spent. The city has been invoiced approximately $12.8 million for a project that has a total budget of $14.4 million. The ground storage tank portion of the project is operational and the plant has been sampled and tested; staff said the final delay is awaiting generator power from the utility provider (CenterPoint) and a small number of remaining items.
Council also asked for context about a water outage that occurred the previous day. Staff explained a contractor for Fulshear Junction was making a connection to the city's 16-inch water main on FM 1093 and "punched through" the pipe instead of creating a controlled connection; the event released a large volume of water and affected customers in Fulshear Lakes and parts of West Fulshear. Staff said service returned toward normal by roughly 7 p.m. after repair work.
Staff emphasized progress on the downtown plant and booster pumps that have improved system pressures this summer. No vote was required for the informational report.