Ithaca district committee endorses $43.9 million capital project plan, eyes Dec. 9 referendum

Ithaca City School District Combined Facilities & Finance Committee Work Session · August 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The combined Facilities and Finance committee recommended that the full board advance a capital project authorizing $43,900,000 in bonding and pursue a tentative Dec. 9 referendum date after required board resolutions and legal notices.

The Ithaca City School District's combined Facilities and Finance committee heard a presentation and recommended that the full board advance a capital project with an estimated referendum cost of $43,900,000 and a tentative December 9 vote date.

Chris Glovitz, lead architect from Tetra Tech, outlined a scope that includes roof-membrane replacement at Boynton, DeWitt and Caroline; renovation of nine science rooms at Boynton and DeWitt; replacement or upgrade of older analog fire-alarm systems at Ithaca High School (two connected systems); HVAC work including geothermal studies and controls upgrades at several schools; charging infrastructure at the transportation center to support bus electrification; abatement and flooring in some buildings; wellness- and nursing-suite renovations to improve ADA compliance; playground replacements; athletics work (including gym floor refinishing and bleacher replacement); and paving/ site work (including Cayuga Heights). Glovitz said the group had tentatively suggested a Dec. 9 vote date and noted the district must meet a state notice requirement (minimum 45 days) ahead of a public referendum.

Dan Bridal, assistant superintendent of operations, and the project team described coordination steps the district will take: convening the architect (Tetra Tech), construction manager (Campus Construction Management), bond counsel and fiscal advisers to finalize cost estimates, legal notifications and communications. Presenters said the $43.9 million figure is a referendum authorization; the district would bond for the project and seek state building aid on eligible items, which presenters estimated would return roughly 58% of eligible costs as state reimbursement.

Committee members agreed to recommend the capital project and timeline to the full board for formal action, with a plan to present details and adopt required resolutions at a September board meeting so timelines and legal notifications meet state requirements. The committee emphasized that the referendum authorizes bonding capacity; specific spending and phased project execution will be managed by administration and reported back to the board.

Why it matters: The project targets multiple facility and safety concerns districtwide and would be funded through bonded debt with state aid offset; approval by voters would authorize the district to borrow for the specified improvements.

Provenance: Presentation began at 00:34:56 with introductions and schedule discussion; scope and the $43.9M referendum amount discussed at 00:47:06.