Seguin ISD bond projects progressing: Barnes near complete, transportation and ag facility advancing, McQueeney on schedule
Summary
District staff reported progress on the 2022 bond: Transportation facility 96% complete, Barnes Middle School about 97% complete and preparing for punch‑list work, Ag Science facility mid‑construction including a 162,000‑gallon fire tank foundation, and McQueeney Elementary roughly 72–75% complete with TxDOT coordination for frontage work.
Seguin ISD project managers told trustees the district’s 2022 bond projects are moving toward completion, with most sites on track and a handful of punch‑list items remaining.
"Transportation currently is 96% complete," project manager Troy Spear said, listing finished items including a perimeter fence, asphalt driveway and a new bus storage bay. He added that the contractor’s outstanding items are largely cosmetic: paint touch‑ups, cleanup and a single parking‑lot light that will be replaced.
Barnes Middle School is nearly finished: the contractor reached substantial completion and teams are addressing minor…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat