Board recommends $37,000 change control to repair cracks found during wet-weather upgrades
Water Resources Board · November 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
During construction of wet-weather upgrades, crews found cracks in concrete walls; the board approved a $37,000 change control to repair the cracks from contingency funds, leaving an estimated remaining contingency of $65,000.
The Water Resources Board recommended a $37,000 change-control to repair concrete cracks discovered during the wet-weather upgrades construction.
Staff said the cracks are outside the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans