Board approves amendment and CBC change order to keep plant lines in service during valve work

Water Resources Board · November 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Water Resources Board approved a $14,300 amendment for SSR design work and a $35,000 CBC change order related to installing access valve boxes and maintaining the 24-inch and 36-inch lines during replacement work at the treatment plant, increasing the CBC contract to $668,360.

The Water Resources Board approved a task-order amendment and a contractor change order to support replacement of two isolation valves at the water treatment plant.

Staff said design complexities extended the SSR design period from an estimated 24 weeks to 38 weeks, and TDEC review took far longer than expected, prompting a $14,300 amendment to the original $65,003.50 task order for SSR. The board approved that amendment.

Separately, staff described a CBC construction change order needed to keep the 24-inch line in service while crews cut out and set new 24- and 36-inch sections and to install valve boxes for future access. That change order added $35,000, bringing the CBC portion of the contract to approximately $668,360. Staff emphasized the work is complex because crews must maintain flow; shutdowns are limited to six to eight hours at a time.

Board members asked whether further change orders were expected; staff said none were foreseen and that contingency funds were in place. The board approved the SSR amendment and the CBC change order by voice vote.

Staff said the SSR amendment will come from reserves and that the larger construction contract will proceed with CBC as the contractor.