DRC flags utility coordination, off‑site permits, traffic shares and roundabout design on Mondich South second submittal
Summary
The DRC reviewed the Mondich South second submittal July 2, 2025; staff emphasized off‑site utility coordination with Orange County, the need to provide final county plans at preconstruction, and detailed traffic, roundabout, stormwater and lighting items that require follow‑up.
Get email alerts on the Large Subdivision topic
No spam. Unsubscribe anytime.
Luke presented the Mondich South second submittal (a large plan set of about 55 sheets) and noted that off‑site utility connections exist in four directions: north, west, southwest and to Effie Drive. Staff asked the applicant to clearly label off‑site utilities on the city plan set and to provide the final county (Orange County) approved road/utility plan set at preconstruction so that city records and contractor documents match the county permit set.
Traffic and signals: city staff said the project will pay proportionate shares for future signal improvements at Effie/Kelly Park and at Effie/Onondage; staff observed the signal warrant for one intersection is not currently met and suggested the future hospital or additional commercial development is likely to trigger construction. Applicant said the traffic impact analysis included the project’s proportionate share and that those figures can be provided.
Roundabout and pedestrian issues: applicant said the roundabout geometry matches FDOT standards and the adjacent Crossroads roundabouts; staff asked that pedestrian refuge islands be re‑examined for the 24‑foot roadway width and agreed to take another look with the appropriate reviewer (Dale).
Stormwater and permits: applicant said a St. Johns permit has been obtained for the project; staff raised a question about which design storm event (the record shows a desire to reconcile 3‑, 4‑ or an alternative storm event standard) and said they would coordinate further with St. Johns and city reviewers.
Lighting, MSBU and Duke Energy: staff requested a photometrics/lighting plan (the city typically requires photometrics) and noted Duke Energy now requires post‑design electric service layouts; the applicant said MSBU coordination is underway and asked the city to accept post‑design Duke coordination where appropriate.
Next steps: applicant will prepare a focused comments response to Dale and schedule a Teams meeting for detailed, sheet‑by‑sheet discussion; staff requested final county‑approved off‑site plans be uploaded at or before preconstruction.