City to buy irrigation pipe materials for Iron West; low bid $92,683
Summary
Council reviewed bids for materials for the Iron West irrigation pipe project. Staff recommended purchasing materials and having the developer install the pipe; the low materials bid was $92,683 from a local supplier and $590,000 is budgeted to the overall pond-and-pump project.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Jonathan Stathis, Cedar City engineering, presented a materials-only purchase for a 24-inch HDPE irrigation pipe that will run from Highway 56 down to newly constructed ponds in the Iron West subdivision. He told the council the city would pay for materials and the developer would install the pipe as part of the broader Iron West drainage and recreation project.
Stathis said the low bidder for the materials was Southwest Plumbing Supply at $92,683. He added the project currently has $590,000 budgeted for the Iron West Irrigation Pond and Pump Station Project and that the materials purchase is separate from installation costs.
Council discussed which budget line would fund the materials; staff said the $590,000 is city-funded and not coming from restricted impact fees or RAP tax. The council indicated the purchase would be placed on the consent agenda for formal approval at a subsequent meeting.
Key technical details: 24-inch diameter corrugated HDPE pipe with smooth interior; low materials bid $92,683; $590,000 total budgeted for the pond and pump station project.