Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Commissioners approve hangar lease language and direct study of displaced runway thresholds starting at west end

November 05, 2025 | Grand County, Colorado


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Commissioners approve hangar lease language and direct study of displaced runway thresholds starting at west end
Airport manager presented a final version of the hangar ground lease and a staff briefing on displaced thresholds and associated costs.

Sean Mori (airport manager) said the updated lease adds an electrical-fee mechanism for new west-side hangars, and the Kremmling lot size was adjusted to 60-by-60 feet (Granby lots will remain 50-by-50). Mori said the electrical costs will be assessed to hangar owners when transformer and meter costs are known rather than as a fixed up-front fee.

A commissioner moved to approve the revised lease language and to apply the concept to both Kremmling and Granby with site-specific customizations. The board approved the motion.

Airport advisory committee member Dennis Carpenter and others discussed displaced threshold options and preliminary cost estimates. Staff and the advisory committee presented high-level cost figures for a phased approach: the west end (09) was presented at roughly $290,000 construction plus roughly $103,000 in engineering costs (about $400,000 total in the presentation), while the east end (27) showed substantially higher costs (roughly $1 million construction plus about $155,000 engineering; staff emphasized the slope and fill requirements could materially increase that estimate). The FAA has approved threshold concepts in the master plan but indicated those projects are not FAA-funded, so the county would need to identify local or private funding or phased approaches.

Commissioners directed staff to seek preliminary, economical concept designs from consultants to scope a first-step project for the west end and to continue investigation of the east end with attention to engineering unknowns and potential funding partners.

Ending: The board approved the hangar lease language, directed staff to pursue consultant work for a west-end displaced threshold concept and to return with cost estimates and funding options.

View full meeting

This article is based on a recent meeting—watch the full video and explore the complete transcript for deeper insights into the discussion.

View full meeting

Sponsors

Proudly supported by sponsors who keep Colorado articles free in 2025

Scribe from Workplace AI
Scribe from Workplace AI