Commissioners approve hangar lease language and direct study of displaced runway thresholds starting at west end
Get AI-powered insights, summaries, and transcripts
SubscribeSummary
Grand County approved revised airport hangar ground-lease language (including electrical-fee allocation and adjusted lot sizes) for Kremmling and Granby hangars and directed staff to pursue staged engineering design and cost estimates for displaced thresholds, beginning with the west (09) end of the runway.
Airport manager presented a final version of the hangar ground lease and a staff briefing on displaced thresholds and associated costs.
Sean Mori (airport manager) said the updated lease adds an electrical-fee mechanism for new west-side hangars, and the Kremmling lot size was adjusted to 60-by-60 feet (Granby lots will remain 50-by-50). Mori said the electrical costs will be assessed to hangar owners when transformer and meter costs are known rather than as a fixed up-front fee.
A commissioner moved to approve the revised lease language and to apply the concept to both Kremmling and Granby with site-specific customizations. The board approved the motion.
Airport advisory committee member Dennis Carpenter and others discussed displaced threshold options and preliminary cost estimates. Staff and the advisory committee presented high-level cost figures for a phased approach: the west end (09) was presented at roughly $290,000 construction plus roughly $103,000 in engineering costs (about $400,000 total in the presentation), while the east end (27) showed substantially higher costs (roughly $1 million construction plus about $155,000 engineering; staff emphasized the slope and fill requirements could materially increase that estimate). The FAA has approved threshold concepts in the master plan but indicated those projects are not FAA-funded, so the county would need to identify local or private funding or phased approaches.
Commissioners directed staff to seek preliminary, economical concept designs from consultants to scope a first-step project for the west end and to continue investigation of the east end with attention to engineering unknowns and potential funding partners.
Ending: The board approved the hangar lease language, directed staff to pursue consultant work for a west-end displaced threshold concept and to return with cost estimates and funding options.
